Home  >  Article  >  Technology peripherals  >  TSMC: A professional team has been established to commit to 2nm R&D tasks

TSMC: A professional team has been established to commit to 2nm R&D tasks

PHPz
PHPzforward
2023-08-18 17:41:111448browse

According to Taiwan Central News Agency, TSMC has established a 2-nanometer task team, called One Team, and mobilized 800 people to conduct simultaneous trial production and mass production in Hsinchu, Baoshan and Kaohsiung factories in Taiwan

In response, TSMC responded today evening that it already has a professional team responsible for 2-nanometer research and development operations, but the staffing details were not disclosed.

TSMC’s Zhongke 2nm plant was originally scheduled to start construction on August 15, but it has now been confirmed that it will be postponed to next year. Therefore, TSMC decided to invest the Kaohsiung plant directly into the 2nm project

TSMC: A professional team has been established to commit to 2nm R&D tasks
##Photo source Pexels
According to our understanding, currently TSMC 2 The main nano production plan will first be carried out in Baoshan, Hsinchu. TSMC has internally designated it as a Fab 20 factory. It plans to build four factories from P1 to P4. P1 is currently progressing intensively and is expected to achieve risk trial production next year and in the second half of 2025. Mass production begins

According to TSMC supply chain sources, TSMC has notified equipment manufacturers to start delivering 2nm related machines from the third quarter of next year. It is expected that the 2nm installation operation of the Kaohsiung plant will be only one month later than that of the Hsinchu Baoshan plant

According to currently known information, TSMC plans to build two 12-inch wafer fabs on the old site of the CNPC Kaohsiung Refinery. The first wafer fab will include 7nm and 6nm wafer fabs with a monthly production capacity of 40,000 wafers in the first phase, and the second wafer fab will include 28nm and 22nm wafer fabs with a monthly production capacity of 20,000 wafers in the second phase. If the investment plan is confirmed, the first phase of the fab will be completed in 2024 and mass production will begin in 2025. However, it seems that for various reasons, TSMC is considering participating in the 2nm project, and the specific plan has not yet been determined

Advertising statement: This article contains external jump links (including but not limited to hyperlinks, QR codes, passwords and other forms), designed to convey more information and save screening time, and are for reference only. Please note that all articles on this site are accompanied by this statement

The above is the detailed content of TSMC: A professional team has been established to commit to 2nm R&D tasks. For more information, please follow other related articles on the PHP Chinese website!

Statement:
This article is reproduced at:ithome.com. If there is any infringement, please contact admin@php.cn delete