Construction start delayed to May 2025, Intel's Fab29 factory in Germany delayed again due to EU subsidy approval

王林
王林Original
2024-06-11 12:00:57452browse

News from this site on May 30, German media Volksstimme reported that Intel's 1nm wafer fab Fab 29 in Germany has been delayed due to black soil cleanup and EU subsidy approval, the new start date has been postponed to 2025 May.

Intel said that the natural start date has been delayed. If the construction and tool installation are accelerated, the factory may still be put into production between the end of 2027 and the beginning of 2028.

The project was scheduled to start in the first half of 2023, but was postponed to the summer of 2024 due to subsidy delays, and the European Competition Authority has not yet approved a €9.9 billion subsidy for the €30 billion project. This resulted in delays in progressing the project.

Intel is adjusting its plans accordingly, focusing on infrastructure construction and land acquisition to prepare for delayed construction.

This site reported on March 23 this year that archaeologists discovered two Neolithic tombs in the Intel factory development area in Magdeburg, Germany, which may cause delays in the construction project.

开工推迟至 2025 年 5 月,英特尔德国 Fab29 工厂因欧盟补贴审批再次延期

According to the previously announced blueprint, Intel purchased a considerable piece of land in Magdeburg. The current phase of Fab29.1 and Fab29.2 The two buildings (blue part in the picture) and supporting facilities occupy only about 1/4 of the total area. This means that Intel is expected to further expand production scale in Germany in the future.

开工推迟至 2025 年 5 月,英特尔德国 Fab29 工厂因欧盟补贴审批再次延期

Fab29.1% and Fab29.2 two factories are three stories high, with each floor height between 5.7 and 6.5 meters. Air-conditioned and heated roof structure, the overall height of the building reaches 36.7 meters. The second floor will be where the High-NA EUV lithography machine is located, and the upper and lower floors are used for material logistics.

The above is the detailed content of Construction start delayed to May 2025, Intel's Fab29 factory in Germany delayed again due to EU subsidy approval. For more information, please follow other related articles on the PHP Chinese website!