How to Calculate Workdays Between Two Dates in SQL Server?

Calculate working days between two dates in SQL Server

Calculating the number of working days between two given dates is a valuable tool for scheduling, time management, and a variety of other business applications. In SQL Server, you can directly calculate the working days from Monday to Friday using T-SQL.

Solution:

To determine the number of working days between two dates (@StartDate and @EndDate), you can use the following formula:

<code class="language-sql">(DATEDIFF(dd, @StartDate, @EndDate) + 1)
- (DATEDIFF(wk, @StartDate, @EndDate) * 2)
- (CASE WHEN DATENAME(dw, @StartDate) = 'Sunday' THEN 1 ELSE 0 END)
- (CASE WHEN DATENAME(dw, @EndDate) = 'Saturday' THEN 1 ELSE 0 END)</code>

Formula breakdown:

  • DATEDIFF(dd, @StartDate, @EndDate) Calculate the total number of days between two dates, including weekends.
  • DATEDIFF(wk, @StartDate, @EndDate) Calculate the number of complete weeks between two dates.
  • (DATEDIFF(wk, @StartDate, @EndDate) * 2) represents the number of weekend days in the specified date range.
  • (CASE WHEN DATENAME(dw, @StartDate) = 'Sunday' THEN 1 ELSE 0 END) Check if the start date is Sunday, if so, subtract 1 day.
  • (CASE WHEN DATENAME(dw, @EndDate) = 'Saturday' THEN 1 ELSE 0 END) Check if the end date is a Saturday, if so, subtract 1 day.

Example:

To calculate the number of working days between October 1, 2008 and October 31, 2008, you can use the following query:

<code class="language-sql">DECLARE @StartDate DATETIME
DECLARE @EndDate DATETIME
SET @StartDate = '2008/10/01'
SET @EndDate = '2008/10/31'

SELECT
   (DATEDIFF(dd, @StartDate, @EndDate) + 1)
  -(DATEDIFF(wk, @StartDate, @EndDate) * 2)
  -(CASE WHEN DATENAME(dw, @StartDate) = 'Sunday' THEN 1 ELSE 0 END)
  -(CASE WHEN DATENAME(dw, @EndDate) = 'Saturday' THEN 1 ELSE 0 END)</code>

This query will return result 22, which represents the number of working days between October 1 and 31, 2008, excluding weekends.